Works successfully completed at Access Storage, Wandsworth

O’Keefe successfully completed the basement works at Access Self Storage, Wandsworth on time and within budget.  Work commenced on site in February 2008 and the completed works were handed over to the Client, Access Storage in June 2009.Well done to the O’Keefe Team for a job well done.

Progress Photos from Access Storage Wandsworth 

 

August 2008

Bulk excavation works underway 

Wandsworth 08.2008-1 Wandsworth 08.2008-2
Wandsworth 09.2008-1 Wandsworth 09.2008-2

 

September 2009

Formation of secant piling wall, capping beams and basement slab

 

December 2008

Construction of basement
level slabs

Wandsworth 12.2008-2 Wandsworth 12.2008-1
Wandsworth 03.2009-1
Wandsworth 03.2009-2

 

 

March 2009

Basement and podium slabs completed.  Steel erectors arrive on site for next phase of contract

 